PHASE D Engineering and Design (2023-24)

The Third Street Improvement Project PHASE D will focus on the nine linear blocks from NE Adams St. to NE Johnson St. and will be addressing the deteriorated downtown infrastructure that has led to accessibility and safety issues. This phase will develop construction documents to 30%, which will help the City access potential State and Federal funding. During this phase, there will be a business resiliency toolkit developed to help downtown businesses prepare for and navigate the construction phase. 

In August 2023, the City of McMinnville awarded the PHASE D contract to BKF Engineers and is expected to be completed by August 2024. This project is funded by City of McMinnville American Rescue Plan Act (ARPA) and McMinnville Urban Renewal funds.  

PHASE D Project Schedule
August 18, 2023 Internal Project Kickoff Meeting
August 21, 2023 Survey and Utility Location Field Work
November 6, 2023 Design Begins
May 6, 2024 15% Design Complete
August 5, 2024 30% Design Complete