2025 Pavement Patching Project

Pavement Patching 2025 Information

Project Overview

This project consists of removing failed sections of existing roadways down to the base section of rock. The base section of rock will be inspected and a new, thicker section of asphalt will be installed to provide smoother sections of roadway to extend the overall roadway’s life.

What to Expect

The pavement patches will be completed in warm, dry weather and patch areas that are opened up will be filled in and completed in the same day. During the repairs, the streets will be down to one lane of alternating traffic with the use of flaggers. Watch for construction signs, no parking signs, and informational public notices prior to, and as the work progresses.

Construction Schedule

July / August 2025. Neighborhood notices will be posted prior to the start of construction.

Project Update - This project was completed on July 14, 2025. It is now in the Warranty Period. Construction costs were as follows:

                                                                         Budget Amount                    $300,000.00

                                                                         Engineering Estimate          $ 279,037.00

                                                                         Contract Amount                 $ 184,685.00

                                                                         Change Order Amount       $  22,920.00

                                                                         Final Construction Cost      $207,605.00

Due to savings in the Contract Amount from the Budgeted Amount and Engineering Estimate, the City was able to combine smaller patches into one larger patch and provide a proper base rock section under one area of the project. These additions help provide a longer lasting final product.